β„‚π•™π•’π•π•π•–π•Ÿπ•˜π•– π•₯𝕠 π•Žπ•šπ•π•π•šπ•€β€™ 𝕔𝕠𝕀π•₯π•šπ•Ÿπ•˜π•€ π• π•Ÿ π•€π•™π• π•£π•šπ•Ÿπ•˜ 𝕦𝕑 π•šπ•Ÿπ•₯𝕖𝕣-π•šπ•€π•π•’π•Ÿπ•• π•€π•–π•£π•§π•šπ•”π•–

β„‚π•™π•’π•π•π•–π•Ÿπ•˜π•– π•₯𝕠 π•Žπ•šπ•π•π•šπ•€β€™ 𝕔𝕠𝕀π•₯π•šπ•Ÿπ•˜π•€ π• π•Ÿ π•€π•™π• π•£π•šπ•Ÿπ•˜ 𝕦𝕑 π•šπ•Ÿπ•₯𝕖𝕣-π•šπ•€π•π•’π•Ÿπ•• π•€π•–π•£π•§π•šπ•”π•–

InterIslander ferry 'Aratere' departs Picton. passing National Geographic research vessel 'Orion'

𝕋𝕙𝕖 π•—π•šπ•Ÿπ•’π•Ÿπ•”π•– π•žπ•šπ•Ÿπ•šπ•€π•₯𝕖𝕣 π•‹π•£π•šπ•”π• π•π•’ π•Žπ•šπ•π•π•šπ•€ π•šπ•€ 𝕀𝕦𝕣𝕖 𝕒𝕝π•₯π•–π•£π•Ÿπ•’π•₯π•šπ•§π•– π•‘π•π•’π•Ÿπ•€ 𝕗𝕠𝕣 π•šπ•Ÿπ•₯𝕖𝕣-π•šπ•€π•π•’π•Ÿπ•• π•£π•–π•€π•šπ•π•šπ•–π•Ÿπ•”π•– π•¨π•šπ•π• 𝕔𝕠𝕀π•₯ 𝕝𝕖𝕀𝕀 π•₯π•™π•’π•Ÿ π•₯𝕙𝕖 π•Ÿπ• π•¨ π••π•–π•—π•¦π•Ÿπ•”π•₯ π•šβ„π•–π• 𝕑𝕣𝕠𝕛𝕖𝕔π•₯ – 𝕓𝕦π•₯ 𝕠π•₯𝕙𝕖𝕣𝕀 π•’π•£π•–π•Ÿβ€™π•₯ π•”π• π•Ÿπ•§π•šπ•Ÿπ•”π•–π••

T

op brass at KiwiRail say it’s disingenuous to quote the final Inter-island Resilient Connection – iReX – figure as a β€œquadrupling” of the original estimate.  

Chief executive Peter Reidy and chair David McLean were at pains to point out to Parliament’s transport select committee that the starting point of $775 million, which dated back to the indicative business case made in November 2018, was unfair. 

β€œYou’d be better to start at the detailed business case,” MacLean said. 

β€œBefore that it was just a random number, a pie in the sky.

β€œMy point is at that stage location hadn’t been identified, but carry on,” Reidy added.  

However, it’s a line Finance Minister Nicola Willis repeated only two hours later, comfortable with the rationale to effectively scrap the project by refusing further Crown funding. 


.



.

β€œThat project had blown out completely and quadrupled in cost and in my view it would keep blowing out in cost. There were massive delivery risks. I don’t think those ships would have been up and running on time. I think we made a good decision,” she said. 

The final cost estimate was $3 billion at the end of November – double the cost from when the detailed business case was developed in June 2021. 

In December Willis confirmed the Crown would not provide the extra $1.4b required since that date. 

RELATED:

Ferries need 'urgent attention', Ministers told before project axed

KiwiRail in talks to cancel contracts for new Interislander ferries

KiwRail considers buying second hand ships for Cook Strait ferry service

As a result, KiwiRail this week confirmed it would be terminating the the contract signed in June 2021 with Hyundai Mipo Dockyard for the two new ships it had procured.

The two rail-enabled ferries would have tripled rail freight capacity, and would be able to carry nearly double the number of passengers compared with the current fleet. 

The commercial opportunity was a critical part of KiwiRail’s quest for financial sustainability, with Reidy repeating to MPs this was about allowing KiwiRail to grow. 

Willis, not convinced by that, described it as a β€œpet project”.

β€œYou know, what’s in the best interests of KiwiRail may not be the same thing as what’s in the best interest of New Zealanders and it’s our job on behalf of taxpayers to think about New Zealanders as a whole, not just KiwiRail.”

As at December 31, 2023, KiwiRail had spent $424 million on the iReX project, not including contract break fees for the ships and other costs, with approximately 150 other contracts to cancel. 

It may also need to undertake remediation works in Picton where there had been plans for an overbridge on Dublin Street. A decision on whether the New Zealand Transport Agency may pick this up has yet to be made. 

Until that happens, Marlborough Mayor Nadine Walker describes the site as a β€œsea of road cones”.

β€œThere’s quite a lot here to be unravelled,” she said. 

But with the Interislander fleet all coming towards end of life (Aratere and Kaiarahi were built in 1999 and Kaitaki was built in 1995), KiwiRail has a much larger task at hand – finding different, suitable vessels, something McLean said would not be straightforward.

Reidy added there were only 22 second-hand ships worldwide that would be suitable to sail the Cook Strait, and none were currently for sale.  

The ferry deal being cut would never be struck again – the cost of procuring the same ships would today cost as much as 40 percent more than the fixed price agreed to in 2021.  

Aside from the ships, Reidy said the terminals in both Wellington and Picton still needed work.  

β€œThe terminals have to be built. New Zealand has to find a solution. Port of Marlborough wharf has probably got about two to three years left; it is in a very end-of-life state. You talk to Centreport, there’s work they’ve got to do as well.” 

Port Marlborough chief executive Rhys Welbourn later told Newsroom the maintenance programme would be reviewed to ensure reliable service for at least another five years.  

β€œWhich, following the comments made today in the hearing, we understand will be some years beyond the life of the current Interislander fleet.” 

The cost escalation for the Wellington terminal was mostly to blame for the project’s blow-out given its location in a high-risk seismic area, something Reidy said only became apparent once the project could progress and further work could be done. 

Despite the explanation, a ministerial advisory group is now tasked with reconciling a plan B. 

The group was confirmed on Thursday and will include former general manager of both the Interislander and Centreport Mark Thompson, Mark Cairns who sits on various transport boards and former National Party minister Roger Sowry.


.



.

But Green Party transport spokesperson Julie Anne Genter said there was no way another option to do all that was required would cost less. 

β€œThere’s no time like the present, it’s going to cost less to carry on with the project as it is now, than to kick it down the road another few years. 

β€œI think that it’s highly unlikely we’re going to get reliable secondhand ships that have the capability and capacity to ensure that we have frequent and sustainable rail connection for freight between the two islands.” 

But Nicola Willis said there were options. 

β€œThere are a number of shipping firms around the world who do have ships. There are lease options, there are buying options, there are secondhand options and that’s why we’re appointing a ministerial advisory group to put all of those options on the table for us.

β€œI’m confident we’ll get a better result for taxpayers, and a better result for ferry users … That’s why I’m appointing a ministerial advisory group so it’s not just KiwiRail giving me views on this.” 

She said the advisory group would also explore which other groups should be responsible for paying for upgrades to port infrastructure.


.

Popular posts from this blog

ℕ𝕖𝕨 β„€π•–π•’π•π•’π•Ÿπ••'𝕀 𝕙𝕒𝕀 𝕒 π•‘π•™π•–π•Ÿπ• π•žπ•–π•Ÿπ•’π• π•šπ•Ÿπ•₯π•–π•£π•Ÿπ•’π•₯π•šπ• π•Ÿπ•’π• 𝕣𝕖𝕑𝕦π•₯𝕒π•₯π•šπ• π•Ÿ, π•₯π•™π•’π•Ÿπ•œπ•€ π•₯𝕠 π•π•’π•”π•šπ•Ÿπ••π•’ π”Έπ•£π••π•–π•£π•Ÿ

𝕀π•₯'𝕀 π•Œπ•Š 𝔼𝕝𝕖𝕔π•₯π•šπ• π•Ÿ 𝔻𝕒π•ͺ π•’π•Ÿπ•• π”Έπ•žπ•–π•£π•šπ•”π•’ 𝕗𝕒𝕔𝕖𝕀 𝕒 𝕀π•₯π•’π•£π•œ π•”π•™π• π•šπ•”π•–

ℕ𝕖𝕨𝕀𝕙𝕦𝕓 π•Ÿπ•–π•¨π•€π•£π• π• π•ž 𝕗𝕒𝕔𝕖𝕀 𝕔𝕝𝕠𝕀𝕦𝕣𝕖 π•šπ•Ÿ π•Žπ•’π•£π•Ÿπ•–π•£ 𝔹𝕣𝕠𝕀. π”»π•šπ•€π•”π• π•§π•–π•£π•ͺ 𝕑𝕣𝕠𝕑𝕠𝕀𝕒𝕝